                        TITLE 21--FOOD AND DRUGS
 
CHAPTER I--FOOD AND DRUG ADMINISTRATION, DEPARTMENT OF HEALTH AND HUMAN 
                          SERVICES (CONTINUED)
 
PART 108 EMERGENCY PERMIT CONTROL--Table of Contents
 
                      Subpart A General Provisions
 
Sec.  108.7  Issuance or denial of permit.

    (a) After a determination and notification by the Commissioner in 
accordance with the provisions of Sec.  108.5 that a manufacturer, 
processor, or packer requires a permit, such manufacturer,

[[Page 206]]

processor, or packer may not thereafter introduce or deliver for 
introduction into interstate commerce any such food manufactured, 
processed, or packed by him unless he holds a permit issued by the 
Commissioner or obtains advance written approval of the Food and Drug 
Administration pursuant to Sec.  108.12(a).
    (b) Any manufacturer, processor, or packer for whom the Commissioner 
has made a determination that a permit is necessary may apply to the 
Commissioner for the issuance of such a permit. The application shall 
contain such data and information as is necessary to show that all 
mandatory requirements and conditions for the manufacturer, processing 
or packing of a food for which regulations are established in subpart B 
of this part are met and, in particular, shall show that the deviations 
specified in the Commissioner's determination of the need for a permit 
have been corrected or suitable interim measures established. Within 10 
working days after receipt of such application, (except that the 
Commissioner may extend such time an additional 10 working days where 
necessary), the Commissioner shall issue a permit, deny the permit, or 
offer the applicant a hearing conducted in accordance with Sec.  108.5 
(b) and (c) as to whether the permit should be issued. The Commissioner 
shall issue such a permit to which shall be attached, in addition to the 
mandatory requirements and conditions of subpart B of this part, any 
additional requirements or conditions which may be necessary to protect 
the public health if he finds that all mandatory requirements and 
conditions of subpart B of this part are met or suitable interim 
measures are established.
    (c) Denial of a permit constitutes final agency action from which 
appeal lies to the courts. The Commissioner will not stay such denial 
pending court appeal except in unusual circumstances, but will 
participate in expediting any such appeal.